Gravel Road Resurfacing Program

Cartoon of Map

Click Here to View the Maintenance Programs Map

Explore our interactive map to access detailed information and the latest updates on current projects and programs managed by the Public Works team.

Gravel Road Rehabilitation Program

Gravel Maintenance and repair is a process of treating roads at the optimum time to maximize their useful life, thus enhancing gravel longevity at the lowest cost. If gravel maintenance and repair is deferred for extended periods of time, roads will rapidly deteriorate and ultimately escalate to failure. Experience shows that spending $1 on gravel maintenance will save or delay spending $6 to $10 on future rehabilitation or reconstruction costs.

Gravel Road Rehabilitation

Challengesf for Road ManagersThe roadway traffic volume and type, resource availability and maintenance capability ultimately dictate how a gravel road is constructed and surfaced. Though gravel roads are typically less expensive to construct, and often less to maintain, the monitoring and maintenance service is more frequent.
Timing of TreatmentWhen average daily traffic volumes (ADT) are within 300 cars per day, the lifespan of a gravel road is between 12 and 15 years. In order to sustain this lifespan anticipation, proper maintenance, chemical treatments and replenishing of surface gravel must be provided.

 

Reconstruction

When necessary, replace/install drainage infrastructure to convey drainage and runoff. When necessary, widen or narrow road to meet minimum surfacing width of 24' with minimum 2' shouler. Correct roadway alignment (vertical and horizontal). Strengthen known "soft spots."

Reconstruction

Rebuild Sub-Base

When able, to reduce construction cost, blend existing materials by balancing the predominte negative material. This may inlude importing reduced volume of material and mixing it on-site to counter balance. 

Rebuild Sub-Base

When necessary, re-establish proper road elevation for drainage and cross-section crown. Build hard stable sub-layer capable of supporting traffic loads and reduce susceptibility to adverse weather affects and wash-out erosion.

Rebuild Sub-Base

Install Base Coarse

When necessary, add base coarse for additional strength on high traffic/loaded roads. Provides a hard and smooth base layer for surface gravel placement. Base coarse allows grader operators to differentiate materials when service grading and prevent over cutting.

Install Base Coarse

Roadway Alignment

Establish roadway schematics to preferred maintenance design standard. Pin (whisker) consistent road width, helping guide equipment operators in placing materials. Establish safe and proper ditch profiles. Establish drive surface and shoulder widths.

Roadway Alignment

Transportation

Material hauling can be the largest obstacle; having too many or not enough trucks can make or break the project schedule. It is estimated that transporting materials to the project is 50-60 percent of the total project cost. Managing long-haul distances with truckload capacity is vital.

Transportation

Gravel Surface Placement

Place surface gravel material, preferably using paver to ensure consistent thickness, crown slope, and lane width. Paver is more efficient and productive by eliminating the number of passes and haul truck wait time. Paver also reduces surface compaction prior to chemical application when used. Surface thickness is vital for continued maintenance grading.

Gravel Surface Placement

Chemical Application

When necessary, chemical application is used to reduce vehicle-generated dust and to improve hardening (binding) of surface gravel. Depending on the chemical and gravel materials, application ranges betweeen .25 gal - 1.75 gal f3.

Chemical Application

Compaction

Because of long graveling distances, initial compaction is achieved using three loaded dump trucks, splitting (offsetting) their wheel tracks. This process expedites compaction efforts whil moisture is present within the gravel.

Compaction

Scratch Pass

A final scratch pass is done to smooth out compaction wheel ruts and relieve vapor build-up from chemical application trapped below the surface. Scratch pass is conducted 1-2 days after completion. Final compaction is done with steel drum and rubber tire rollers, sealing in chemical and aggregates.

Scratch Pass

Results

Gravel roads will always have distress and need service, specifically after heavy moisture. Weather impacts can be reduced when quality materials and construction practices are used. Drainage, road profile, good gravel and chemical stabilizing must be part of the process.

Results